Haselden remodeled Smoky Hill High School in Aurora, Colo. Our improvements touched 300,000 square feet of existing school space and included an roughly 5,600 expansion to the school’s swimming pool.

The remodel was fast-paced because it started when school ended for the summer and had to be completed before the staff and students returned. In about nine weeks, Haselden worked quickly and efficiently to install new flooring in corridors, new casework in science classrooms, new ceiling tiles throughout, nearly new lights throughout. Our interior work included a lot of painting.

The pool addition required demolition of both existing pools in their entirety. Haselden built two new pools (lap pool and dive pool) heated by solar energy.