Haselden provided CM/CG services for the City and County of Broomfield Detention Center and Police Department Training Facility.

The previous detention center and training facility was an approximately 50,000 SF, two-story facility constructed in 2001. The project included adding 200 beds, 30,000 gross SF, and renovating 10,000 SF. Haselden provided detail conceptual estimating during the design development phase to ensure the best value in design and construction for the owner.

The facility remained operational and occupied during construction.

At a glance

  • Owner City and County of Broomfield
  • Architect Roth + Sheppard Architects
  • Delivery method
  • CM/GC
  • Project size 40,000 SF
  • Construction cost$16 million
  • Completed September 2010